  How Does Offshore Pipeline Installation Work?

Laying pipe on the seafloor can pose a number of challenges, especially if the water is deep. There are three main ways that subsea pipe is laid -- S-lay, J-lay and tow-in -- and the pipelay vessel is integral to the success of the installation.
Buoyancy affects the pipelay process, both in positive and negative ways. In the water, the pipe weighs less if it is filled with air, which puts less stress on the pipelay barge. But once in place on the sea bed, the pipe requires a downward force to remain in place. This can be provided by the weight of the oil passing through the pipeline, but gas does not weigh enough to keep the pipe from drifting across the seafloor. In shallow-water scenarios, concrete is poured over the pipe to keep it in place, while in deepwater situations, the amount of insulation and the thickness required to ward of hydrostatic pressure is usually enough to keep the line in place.
Tow-In Pipeline Installation
While jumpers are typically short enough to be installed in sections by ROVs, flowlines and pipelines are usually long enough to require a different type of installation, whether that is tow-in, S-lay or J-lay.
Tow-in installation is just what it sounds like; here, the pipe is suspended in the Stingers, measuring up to 300 feet (91 meters) long, extend from the stern to support the pipe as it is moved into the water, as well as control the curvature of the installation. Some pipelay barges have adjustable stingers, which can be shortened or lengthened according to the water depth.
Pipe being lowered into the water via a stinger for S-lay installation
Pipe being lowered into the water via a stinger for S-lay installationSource: www.nord-stream.com
Proper tension is integral during the S-lay process, which is maintained via tensioning rollers and a controlled forward thrust, keeping the pipe from buckling. S-lay can be performed in waters up to 6,500 feet (1,981 meters) deep, and as many as 4 miles (6 kilometers) a day of pipe can be installed in this manner.
J-Lay Pipeline Installation
Overcoming some of the obstacles of S-lay installation, J-lay pipeline installation puts less stress on the pipeline by inserting the pipeline in an almost vertical position. Here, pipe is lifted via a tall tower on the boat, and inserted into the sea. Unlike the double curvature obtained in S-lay, the pipe only curves once in J-lay installation, taking on the shape of a "J" under the water.
J-Lay Pipeline Installation
J-Lay Pipeline InstallationSource: www.technip.com
The reduced stress on the pipe allows J-lay to work in deeper water depths. Additionally, the J-lay pipeline can withstand more motion and underwater currents than pipe being installed in the S-lay fashion.
J-Lay Pipelay Vessel S7000
J-Lay Pipelay Vessel S7000Source: www.hydro.com
Types Of Pipelay Vessels
There are three main types of pipelay vessels. There are J-lay and S-lay barges that include a welding station and lifting crane on board. The 40- or 80-foot (12- or 24-meter) pipe sections are welded away from wind and water, in an enclosed environment. On these types of vessels, the pipe is laid one section at a time, in an assembly-line method.
On the other hand, reel barges contain a vertical or horizontal reel that the pipe is wrapped around. Reel barges are able to install both smaller diameter pipe and flexible pipe. Horizontal reel barges perform S-lay installation, while vertical reel barges can perform both S-lay and J-lay pipeline installation.
Vertical Reel Barge
Vertical Reel BargeSource: www.jee.co.uk
When using reel barges, the welding together of pipe sections is done onshore, reducing installation costs. Reeled pipe is lifted from the dock to the vessel, and the pipe is simply rolled out as installation is performed. Once all of the pipe on the reel has been installed, the vessel either returns to shore for another, or some reel barges are outfitted with cranes that can lift a new reel from a transport vessel and return the spent reel, which saves time and money.



                                                    pipeline barge
 
  
    
                                                       RISER INSTALLATION
    
   
                                           jacket installation
   
    
   
  
 
 
  
  
                                                                   Diving Work
 
   
  
 

Sunday, December 26, 2010

Pengayau Iban

                                              Gambar pengayau bansa iban
                                     

File:COLLECTIE TROPENMUSEUM Een Ibu Dajak krijger uit Long Nawan Z. en O. afdeling Borneo. TMnr 60034031.jpg